A. Sewer mains shall be installed by the subdivider or his contractor as shown on drawings as approved by the City Engineer. Sewer mains, manholes, lamp poles, and lift stations and force mains when required shall be installed in all subdivisions prior to any water service being connected to any improvements.

B. Should the subdivider be required to install sewer mains larger than eight inches (8") in diameter or lift stations and force mains larger than his subdivision requirements to implement the development of the Comprehensive Plan, the city will negotiate the installation of the required sewer facilities and reimburse the subdivider for the additional costs for the larger facilities (materials only). If bids are required, a percentage of cost will be determined prior to bid award.