A. Upon receipt of the final subdivision application and plat, the Plat Administrator shall, within two (2) working days of receipt, distribute copies to all offices, departments, and agencies receiving the preliminary plat. Each office, department, or agency shall file written recommendations with the Plat Administrator within fifteen (15) days from the date of filing of the final plat with the Plat Administrator. If any such office, department, or agency fails to file a recommendation within the time limitation, it may be presumed that such office, department, or agency has no recommendations for final plat approval shall not modify the terms of preliminary plat recommendations without the written consent of the subdivider.

B. Within fifteen (15) days of filing of the final plat the City Engineer shall review the final plat and submit to the Plat Administrator a written report with respect to the following conditions:

1. That the proposed final plat bears the required certificates and statements of approval.

2. That a title report furnished by the subdivider confirms the title of the land and the proposed subdivision is vested in the name of the owner whose signature appears on the plat certificate.

3. That the facilities and improvements required to be provided by the subdivider have been completed or alternatively that the subdivider has submitted with the proposed final plat a performance bond or other security in conformance with Section 18.17.090 of this chapter.

4. That the plat is technically correct as certified by the land surveyor responsible for the plat.

C. Within fifteen (15) days of filing of the final plat, the Grant County Health District or other agency furnishing sewage disposal and supplying water shall review the final plat and submit to the Plat Administrator a written report recommending approval or disapproval of the final plat as to the adequacy of the proposed means of sewage disposal and water supply.

D. Within fifteen (15) days of filing of the final plat the appropriate irrigation district serving or from which the real property is entitled to be served with irrigation water shall review the final plat and submit to the Plat Administrator a written report recommending approval or disapproval of the final plat as to the adequacy of the proposed means of the delivery of irrigation district entitlement water and as to the adequacy of the proposed means of removal of irrigation waste water.

E. Within twenty (20) days of filing of the final plat the Planning Authority shall review the final plat as to compliance with all terms of the preliminary approval of the proposed plat subdivision or dedication and shall recommend to the City Council that said plat be approved or disapproved.

F. Council Action:

1. The Council shall, within thirty (30) days from the date of filing of the final subdivision application and plat, approve of disapprove the final plat unless the subdivider consents to an extension of such time period in writing.

2. If the Council finds that the subdivision proposed for final plat approval conforms to all terms of the preliminary plat approval, the requirements of RCW Chapter 58.17, other applicable state laws, and any other requirements which were in effect at the time of preliminary plat approval, it shall approve the final plat and by such action direct the Mayor to sign the plat.